NASA-LLIS-3636: Lessons Learned – Different Groups in Different Locations Working On the Same System but Under Different Contracts
Abstract: The Microwave Scanning Beam Landing System (MSBLS) contract, originally controlled by Johnson Space Center (JSC), was split across NASA centers. The Kennedy Space Center (KSC) has operation and maintenance (O&M) responsibility ...
NASA-LLIS-2042: Lessons Learned – Each NASA Project Should Assess Its Compliance with NASA Lessons Learned
Abstract: Abstract:
NASA has been criticized for failing to systematically make use of information in the NASA Lesson Learned Information System. Mars Exploration Rover, Kepler, and Juno are examples of major ...
NASA has been criticized for failing to systematically make use of information in the NASA Lesson Learned Information System. Mars Exploration Rover, Kepler, and Juno are examples of major ...
NASA-LLIS-2041: Lessons Learned – MRO Spaceflight Computer Side Swap Anomalies [Export Version]
Abstract: Abstract:
A few months into its mission, MRO began experiencing unexpected side swaps to the redundant flight computer that placed the spacecraft into safe mode. The problem was traced to subtle ...