Lessons Learned - Integrate Earned Value Management Tools With the Project Management System

contributor authorNASA - National Aeronautics and Space Administration (NASA)
date accessioned2017-09-04T18:22:59Z
date available2017-09-04T18:22:59Z
date copyright04/04/2012
date issued2012
identifier otherICWBXEAAAAAAAAAA.pdf
identifier urihttp://yse.yabesh.ir/std;query=autho162sear3FCDCAC426159DD6E273C9F4A/handle/yse/205391
description abstractFor EVM to apply timely and effective corrective action to minimize cost overruns, it must be fully integrated with the project management systems that supply up-to-date budget, schedule, and cost data. EVM pilot exercises performed on two NASA projects were constrained by the inability to adequately "feed" the automated EVM analysis tool with the data needed to generate EVM products. The financial and scheduling systems for managing the NASA project and providing configuration control must be sufficiently mature to support the integration of an EVM process into the project.
languageEnglish
titleNASA-LLIS-6496num
titleLessons Learned - Integrate Earned Value Management Tools With the Project Management Systemen
typestandard
page3
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;2012
contenttypefulltext


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record