Show simple item record

Lessons Learned - Control of Temporary Installations (Wire Harness Fit Check)

contributor authorNASA - National Aeronautics and Space Administration (NASA)
date accessioned2017-09-04T18:37:11Z
date available2017-09-04T18:37:11Z
date copyright05/29/1998
date issued1998
identifier otherJMVEQCAAAAAAAAAA.pdf
identifier urihttp://yse.yabesh.ir/std;query=authoCA5893FD081D49A96159DD6EFDEC014A/handle/yse/219081
description abstractDescription of Driving Event:
A wire harness was installed on a flight unit for a fit check. Subsequent manufacturing operations were continued through several steps until it was realized that the wire harness was meant to be a temporary installation only. Production time was lost to back out and remove the harness so that it could be returned to its manufacturer to complete its detail manufacturing sequence and final test. This incident caused a slight impact (delay) to subcontractor's internal schedule, but had no effect on overall Program schedule.
Root cause: During the Manufacturing process it is very important to flag and control "temporary installations" to avoid wasting time or, in the worst case, building in sub-assemblies that are incomplete and/or untested.
languageEnglish
titleNASA-LLIS-1258num
titleLessons Learned - Control of Temporary Installations (Wire Harness Fit Check)en
typestandard
page2
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;1998
contenttypefulltext
subject keywordsConfiguration Management
subject keywordsIndustrial Operations
subject keywordsPackaging Handling Storage
subject keywordsParts Materials & Processes
subject keywordsPolicy & Planning
subject keywordsSafety & Mission Assurance


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record