Lessons Learned – Facilities, Mod & Rehab, Added Team Membe

contributor authorNASA - National Aeronautics and Space Administration (NASA)
date accessioned2017-09-04T16:57:28Z
date available2017-09-04T16:57:28Z
date copyright08/23/1999
date issued1999
identifier otherXGTEQCAAAAAAAAAA.pdf
identifier urihttps://yse.yabesh.ir/std/handle/yse/120963
description abstractDescription of Driving Event:
The Mod and Rehab projects are typically requiring that people be moved out of offices while the construction activity is taking place. As a result, there is an extra burden on the Project Manager to coordinate people moves. Along with the moves come the issues of telephone and computer moves, because different organizations handle these moves. In addition, there is also the issue of where are the people going to be temporarily moved to.
During the planning phases of moves, it becomes a full-time job to coordinate all the above activities.
languageEnglish
titleNASA-LLIS-0860num
titleLessons Learned – Facilities, Mod & Rehab, Added Team Membeen
typestandard
page2
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;1999
contenttypefulltext
subject keywordsAdministration/Organization
subject keywordsFacilities


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record