description abstractAbstract:
The CLCS project was initiated in FY 1997 to modernize the Launch Processing System (LPS) that was engineered and developed in the 1970s. The modernization was needed to ensure continued safe and dependable launch support for the Shuttle program. Per initial planning, CLCS was projected to reduce the costs for Shuttle operations at KSC, in addition to being an architecture in place that would support future planning and new program activities to occur at KSC. The CLCS project experienced many significant challenges even from the project startup (i.e., time and resources that included both funding and manpower).
This lesson document covers project/program management, systems engineering, and safey and mission assurance.
languageEnglish
titleNASA-LLIS-1851num
titleLessons Learned - KSC Checkout and Launch Control System (CLCS) - Project, Systems, SM&Aen
typestandard
page3
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;2009
contenttypefulltext
subject keywordsAdditional Categories.Launch Process
subject keywordsAdditional Categories.Launch Vehicle