Lessons Learned - Mobile Launch Platform (MLP) Air-arcing Operation

contributor authorNASA - National Aeronautics and Space Administration (NASA)
date accessioned2017-09-04T15:19:59Z
date available2017-09-04T15:19:59Z
date copyright07/30/1992
date issued1992
identifier otherMUYCQCAAAAAAAAAA.pdf
identifier urihttps://yse.yabesh.ir/std/handle/yse/19856
description abstractDescription of Driving Event:
During air-arcing operations under mobile launch platform-1 (MLP), a welder smelled smoke through the hole he was working on and found a fire in the floor insulation of compartment 16B. Investigation revealed that air-arcing under MLP-1 ignited hydraulic fluid that had accumulated in the floor insulation of compartment 16B. Hydraulic pumping units leaked hydraulic fluid onto the insulation for several years. Hot particles released by air-arcing blew into compartment 16B as the welder penetrated the MLP bottom panel, and the fluid ignited.
languageEnglish
titleNASA-LLIS-0118num
titleLessons Learned - Mobile Launch Platform (MLP) Air-arcing Operationen
typestandard
page2
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;1992
contenttypefulltext
subject keywordsFacilities