Lessons Learned - Emergency Procedure Training for Critical Operations/Areas

contributor authorNASA - National Aeronautics and Space Administration (NASA)
date accessioned2017-09-04T15:26:20Z
date available2017-09-04T15:26:20Z
date copyright04/04/1991
date issued1991
identifier otherNOBEQCAAAAAAAAAA.pdf
identifier urihttps://yse.yabesh.ir/std/handle/yse/27077
description abstractDescription of Driving Event:
While installing electrical cables into a conduit in the Johnson Space Center Mission Control Room, the conduit was displaced from its mounting, and then contacted and broke a chilled water line. A portion of the room was flooded. The installation procedures did not include details for using sufficient lubrication on the cables being pulled through the conduit. Also, no cautions or warnings were provided to alert the electricians to take additional precautions to prevent accidents in a high value, mission essential area. Other factors that increased the extent of damage included; (1) An emergency plan that did not include water leaks, and (2) No information was available to the maintenance or operations personnel on the location of or access to shutoff systems. The investigation board recommended correcting the deficiencies in the work procedures, emergency plans, and Mission Control allowable work policies. Also recommended was increased training of personnel to include these improvements.
languageEnglish
titleNASA-LLIS-0450num
titleLessons Learned - Emergency Procedure Training for Critical Operations/Areasen
typestandard
page2
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;1991
contenttypefulltext
subject keywordsEmergency Preparedness
subject keywordsFacilities