Lessons Learned – Criticality of Hardware Refurbishment Process

contributor authorNASA - National Aeronautics and Space Administration (NASA)
date accessioned2017-09-04T15:07:09Z
date available2017-09-04T15:07:09Z
date copyright07/20/1999
date issued1999
identifier otherLHCEQCAAAAAAAAAA.pdf
identifier urihttps://yse.yabesh.ir/std/handle/yse/4838
description abstractDescription of Driving Event:
Shortly after launch of STS-90, some of the motors/air-pumps associated with the aquatic habitats exhibited an increased power draw indicating either motor or pump failure. To successfully complete the mission, an in-flight procedure was utilized to cross-link each habitat to an operational air pump. Upon landing and recovery, an investigation was conducted of the failed motor/air-pump assemblies to determine why some units failed while others performed normally. The investigation determined that all of the units that operated properly were original equipment manufacture units, and the units that failed had all been refurbished.
languageEnglish
titleNASA-LLIS-0627num
titleLessons Learned – Criticality of Hardware Refurbishment Processen
typestandard
page2
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;1999
contenttypefulltext
subject keywordsFlight Equipment
subject keywordsHardware
subject keywordsParts Materials & Processes
subject keywordsPayloads
subject keywordsResearch & Development
subject keywordsSafety & Mission Assurance
subject keywordsTest & Verification