description abstractAbstract:
The over-current detection scheme for Deep Impact spacecraft heater circuitry failed to detect an over-current condition during ground test due to an inadequate circuit design and test design. The root cause was inadequate contractor oversight and peer review. The lessons learned from the MCO mission loss on the value of detailed technical review and contractor oversight must be reemphasized, and test configurations should be subjected to FMEA and feature positive controls limiting electrical current.
languageEnglish
titleNASA-LLIS-1711num
titleLessons Learned - Deep Impact Reiterates the Need for Peer Review and Contractor Oversight (2005)en
typestandard
page4
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;2005
contenttypefulltext
subject keywordsAdditional Categories.
subject keywordsAdditional Categories.Flight Equipment
subject keywordsAdditional Categories.Ground Equipment
subject keywordsAdditional Categories.Ground Operations
subject keywordsAdditional Categories.Hardware
subject keywordsAdditional Categories.Payloads
subject keywordsAdditional Categories.Spacecraft
subject keywordsAdditional Categories.Test Article


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record