NASA-LLIS-0047
Lessons Learned - Mercoid Pressure Switch; Inadvertent Water Deluge Activation
| contributor author | NASA - National Aeronautics and Space Administration (NASA) | |
| date accessioned | 2017-09-04T18:19:07Z | |
| date available | 2017-09-04T18:19:07Z | |
| date copyright | 33591 | |
| date issued | 1991 | |
| identifier other | AFYCQCAAAAAAAAAA.pdf | |
| identifier uri | http://yse.yabesh.ir/std;jsery=autho162s7D8308/handle/yse/201818 | |
| description abstract | Description of Driving Event: The primary cause of the mishap was an activation (closing) of the fire pump mercoid pressure switch which prematurely started the fire pump. This produced transient pressures that exceeded the 2:1 mechanical advantage of the deluge valves, forcing them open. The switch activation was caused by potable water system pressure fluctuations external to the local facility. | |
| language | English | |
| title | NASA-LLIS-0047 | num |
| title | Lessons Learned - Mercoid Pressure Switch; Inadvertent Water Deluge Activation | en |
| type | standard | |
| page | 2 | |
| status | Active | |
| tree | NASA - National Aeronautics and Space Administration (NASA):;1991 | |
| contenttype | fulltext | |
| subject keywords | Facilities | |
| subject keywords | Fire Protection | |
| subject keywords | Ground Equipment | |
| subject keywords | Ground Operations | |
| subject keywords | Hardware |

درباره ما