Abstract: The scope of this Standard is to address the unit/plant demand development subsystem for boilers with steaming capacities of 200,000 lbs/hr (25 kg/s) or greater. This subsystem includes firing rate demand development, throttle/header pressure control, and unit megawatt/steam flow control as applicable.
This Standard will address two types of process applications:
a) a single boiler supplying a single turbine, typical of an electric utility power plant; and
b) a single boiler or multiple boilers supplying a common distribution header, typical of an industrial power plant.
Specifically excluded from consideration are:
a) dispatch control;
b) turbine/generator control (other than turbine demand);
c) combustion controls (covered separately by ANSI/ISA–77.41.01, Fossil Fuel Power Plant Boiler Combustion Controls);
d) steam distribution control systems;
e) economic loading of boilers; and
f) fluidized bed boilers.
Purpose
The purpose of this document is to establish the minimum requirements for the functional design specifications of unit/plant demand development for control systems for drum-type fossil-fueled power plant boilers.
This Standard will address two types of process applications:
a) a single boiler supplying a single turbine, typical of an electric utility power plant; and
b) a single boiler or multiple boilers supplying a common distribution header, typical of an industrial power plant.
Specifically excluded from consideration are:
a) dispatch control;
b) turbine/generator control (other than turbine demand);
c) combustion controls (covered separately by ANSI/ISA–77.41.01, Fossil Fuel Power Plant Boiler Combustion Controls);
d) steam distribution control systems;
e) economic loading of boilers; and
f) fluidized bed boilers.
Purpose
The purpose of this document is to establish the minimum requirements for the functional design specifications of unit/plant demand development for control systems for drum-type fossil-fueled power plant boilers.
Collections
:
Show full item record
contributor author | ISA - International Society of Automation | |
date accessioned | 2017-09-04T16:40:26Z | |
date available | 2017-09-04T16:40:26Z | |
date copyright | 01/01/2002 (R 2008) | |
date issued | 2008 | |
identifier other | VNKLLCAAAAAAAAAA.pdf | |
identifier uri | http://yse.yabesh.ir/std;jsessionid=A33FFBB4A04818B251172099FA6814F7/handle/yse/104026 | |
description abstract | The scope of this Standard is to address the unit/plant demand development subsystem for boilers with steaming capacities of 200,000 lbs/hr (25 kg/s) or greater. This subsystem includes firing rate demand development, throttle/header pressure control, and unit megawatt/steam flow control as applicable. This Standard will address two types of process applications: a) a single boiler supplying a single turbine, typical of an electric utility power plant; and b) a single boiler or multiple boilers supplying a common distribution header, typical of an industrial power plant. Specifically excluded from consideration are: a) dispatch control; b) turbine/generator control (other than turbine demand); c) combustion controls (covered separately by ANSI/ISA–77.41.01, Fossil Fuel Power Plant Boiler Combustion Controls); d) steam distribution control systems; e) economic loading of boilers; and f) fluidized bed boilers. Purpose The purpose of this document is to establish the minimum requirements for the functional design specifications of unit/plant demand development for control systems for drum-type fossil-fueled power plant boilers. | |
language | English | |
title | ISA 77.43.01 | num |
title | Fossil Fuel Power Plant Unit/Plant Demand Development – Drum Type | en |
type | standard | |
page | 30 | |
status | Active | |
tree | ISA - International Society of Automation:;2008 | |
contenttype | fulltext |