NASA-LLIS-1091
Lessons Learned – Synchronizing Customer Requirements with Service Provisions
Year: 1999
Abstract: Description of Driving Event:
During pre-operations for the 5A US Lab Closed Hatch Environmental Control & Life Support System/Thermal Control System (ECLSS/TCS) testing, a water separator fault occurred in the Common Cabin Air Assembly (CCAA). The inlet ORU was pulled and found to be wet inside. Three to four ounces of water were noted on the rack floor under the separator/heat exchanger. A small amount of water was found inside the separator but not enough to touch electronics. Water was also found in other areas (hydroflow fitting and coupler of the inlet hose and the inside of the inlet).
Root cause: The Test Procedure (TP) and Test Preparaton and Restoration Document (TP&RD) were not synchronized. The TP&RD placed a valve in series between the water separator and the GSE collection tank. The TP&RD also, appropriately, had the valve closed to keep water in the line after it was filled and before water separator was started. The TP did not open the valve before initaiation of water separator operations. The TP&RD & TP WERE NOT carefully reviewed for complete integration.
During pre-operations for the 5A US Lab Closed Hatch Environmental Control & Life Support System/Thermal Control System (ECLSS/TCS) testing, a water separator fault occurred in the Common Cabin Air Assembly (CCAA). The inlet ORU was pulled and found to be wet inside. Three to four ounces of water were noted on the rack floor under the separator/heat exchanger. A small amount of water was found inside the separator but not enough to touch electronics. Water was also found in other areas (hydroflow fitting and coupler of the inlet hose and the inside of the inlet).
Root cause: The Test Procedure (TP) and Test Preparaton and Restoration Document (TP&RD) were not synchronized. The TP&RD placed a valve in series between the water separator and the GSE collection tank. The TP&RD also, appropriately, had the valve closed to keep water in the line after it was filled and before water separator was started. The TP did not open the valve before initaiation of water separator operations. The TP&RD & TP WERE NOT carefully reviewed for complete integration.
Subject: Configuration Management
Show full item record
| contributor author | NASA - National Aeronautics and Space Administration (NASA) | |
| date accessioned | 2017-09-04T16:42:27Z | |
| date available | 2017-09-04T16:42:27Z | |
| date copyright | 07/15/1999 | |
| date issued | 1999 | |
| identifier other | VRUEQCAAAAAAAAAA.pdf | |
| identifier uri | https://yse.yabesh.ir/std/handle/yse/105754 | |
| description abstract | Description of Driving Event: During pre-operations for the 5A US Lab Closed Hatch Environmental Control & Life Support System/Thermal Control System (ECLSS/TCS) testing, a water separator fault occurred in the Common Cabin Air Assembly (CCAA). The inlet ORU was pulled and found to be wet inside. Three to four ounces of water were noted on the rack floor under the separator/heat exchanger. A small amount of water was found inside the separator but not enough to touch electronics. Water was also found in other areas (hydroflow fitting and coupler of the inlet hose and the inside of the inlet). Root cause: The Test Procedure (TP) and Test Preparaton and Restoration Document (TP&RD) were not synchronized. The TP&RD placed a valve in series between the water separator and the GSE collection tank. The TP&RD also, appropriately, had the valve closed to keep water in the line after it was filled and before water separator was started. The TP did not open the valve before initaiation of water separator operations. The TP&RD & TP WERE NOT carefully reviewed for complete integration. | |
| language | English | |
| title | NASA-LLIS-1091 | num |
| title | Lessons Learned – Synchronizing Customer Requirements with Service Provisions | en |
| type | standard | |
| page | 3 | |
| status | Active | |
| tree | NASA - National Aeronautics and Space Administration (NASA):;1999 | |
| contenttype | fulltext | |
| subject keywords | Configuration Management | |
| subject keywords | Flight Equipment | |
| subject keywords | Flight Operations | |
| subject keywords | Ground Equipment | |
| subject keywords | Ground Operations | |
| subject keywords | Hardware | |
| subject keywords | Industrial Operations | |
| subject keywords | Launch Process | |
| subject keywords | Parts Materials & Processes | |
| subject keywords | Policy & Planning | |
| subject keywords | Range Operations | |
| subject keywords | Research & Development | |
| subject keywords | Risk Management/Assessment | |
| subject keywords | Safety & Mission Assurance | |
| subject keywords | Test & Verification | |
| subject keywords | Test Article | |
| subject keywords | Test Facility |

درباره ما