• 0
    • ارسال درخواست
    • حذف همه
    • Industrial Standards
    • Defence Standards
  • درباره ما
  • درخواست موردی
  • فهرست استانداردها
    • Industrial Standards
    • Defence Standards
  • راهنما
  • Login
  • لیست خرید شما 0
    • ارسال درخواست
    • حذف همه
View Item 
  •   YSE
  • Defence Standards
  • NASA - National Aeronautics and Space Administration (NASA)
  • View Item
  •   YSE
  • Defence Standards
  • NASA - National Aeronautics and Space Administration (NASA)
  • View Item
  • All Fields
  • Title(or Doc Num)
  • Organization
  • Year
  • Subject
Advanced Search
JavaScript is disabled for your browser. Some features of this site may not work without it.

Archive

NASA-LLIS-1218

Lessons Learned – Substantial Benefits to Projects from the Use of a Blanket Purchase Agreement for Procurement

Organization:
NASA - National Aeronautics and Space Administration (NASA)
Year: 2002

Abstract: Description of Driving Event:
A project required purchase of an indefinite quantity of hardware spread over several years. The hardware was procured for this project using a modified Blanket Purchase Agreement (BPA) which resulted in cost savings to the project, simplified procurement and good service from the vendor. In addition, the BPA set prices for the hardware at the beginning of the contract and having this information allowed better planning for material purchases.
URI: https://yse.yabesh.ir/std/handle/yse/130629
Subject: Configuration Management
Collections :
  • NASA - National Aeronautics and Space Administration (NASA)
  • Download PDF : (15.06Kb)
  • Show Full MetaData Hide Full MetaData
  • Statistics

    NASA-LLIS-1218

Show full item record

contributor authorNASA - National Aeronautics and Space Administration (NASA)
date accessioned2017-09-04T17:07:04Z
date available2017-09-04T17:07:04Z
date copyright06/17/2002
date issued2002
identifier otherYGVEQCAAAAAAAAAA.pdf
identifier urihttps://yse.yabesh.ir/std/handle/yse/130629
description abstractDescription of Driving Event:
A project required purchase of an indefinite quantity of hardware spread over several years. The hardware was procured for this project using a modified Blanket Purchase Agreement (BPA) which resulted in cost savings to the project, simplified procurement and good service from the vendor. In addition, the BPA set prices for the hardware at the beginning of the contract and having this information allowed better planning for material purchases.
languageEnglish
titleNASA-LLIS-1218num
titleLessons Learned – Substantial Benefits to Projects from the Use of a Blanket Purchase Agreement for Procurementen
typestandard
page3
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;2002
contenttypefulltext
subject keywordsConfiguration Management
subject keywordsGround Equipment
subject keywordsHardware
subject keywordsLogistics
subject keywordsParts Materials & Processes
subject keywordsProcurement Small Business & Industrial Relations
subject keywordsResearch & Development
DSpace software copyright © 2017-2020  DuraSpace
نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
yabeshDSpacePersian
 
DSpace software copyright © 2017-2020  DuraSpace
نرم افزار کتابخانه دیجیتال "دی اسپیس" فارسی شده توسط یابش برای کتابخانه های ایرانی | تماس با یابش
yabeshDSpacePersian