Lessons Learned - Next Generation Launch Technology (NGLT)- Plan for and Adequately Staff the Project Team
Year: 2004
Abstract: Abstract:
A lack of adequate workforce in the early days of the project delayed development of plans and complicated the project's formulation. Each project should be treated as a new effort with adequate staff from the outset.
A lack of adequate workforce in the early days of the project delayed development of plans and complicated the project's formulation. Each project should be treated as a new effort with adequate staff from the outset.
Subject: Policy & Planning
Show full item record
| contributor author | NASA - National Aeronautics and Space Administration (NASA) | |
| date accessioned | 2017-09-04T15:27:36Z | |
| date available | 2017-09-04T15:27:36Z | |
| date copyright | 07/01/2004 | |
| date issued | 2004 | |
| identifier other | NRWEQCAAAAAAAAAA.pdf | |
| identifier uri | https://yse.yabesh.ir/std/handle/yse/28559 | |
| description abstract | Abstract: A lack of adequate workforce in the early days of the project delayed development of plans and complicated the project's formulation. Each project should be treated as a new effort with adequate staff from the outset. | |
| language | English | |
| title | NASA-LLIS-1515 | num |
| title | Lessons Learned - Next Generation Launch Technology (NGLT)- Plan for and Adequately Staff the Project Team | en |
| type | standard | |
| page | 2 | |
| status | Active | |
| tree | NASA - National Aeronautics and Space Administration (NASA):;2004 | |
| contenttype | fulltext | |
| subject keywords | Policy & Planning | |
| subject keywords | Program and Project Management | |
| subject keywords | Research & Development | |
| subject keywords | Risk Management/Assessment |

درباره ما