Lessons Learned – Pre-Ship Review
Year: 2000
Abstract: Practice:
Prior to shipment of hardware or software, conduct a pre-ship review at the completion of the fabrication or build and testing of the item to be shipped. This review is scheduled as part of the overall technical review program as defined in a project review plan. Pre-ship review is held at the supplier or NASA facility where the item was made and tested.
Prior to shipment of hardware or software, conduct a pre-ship review at the completion of the fabrication or build and testing of the item to be shipped. This review is scheduled as part of the overall technical review program as defined in a project review plan. Pre-ship review is held at the supplier or NASA facility where the item was made and tested.
Show full item record
| contributor author | NASA - National Aeronautics and Space Administration (NASA) | |
| date accessioned | 2017-09-04T16:20:34Z | |
| date available | 2017-09-04T16:20:34Z | |
| date copyright | 03/07/2000 | |
| date issued | 2000 | |
| identifier other | BMCEQCAAAAAAAAAA.pdf | |
| identifier uri | https://yse.yabesh.ir/std/handle/yse/84002 | |
| description abstract | Practice: Prior to shipment of hardware or software, conduct a pre-ship review at the completion of the fabrication or build and testing of the item to be shipped. This review is scheduled as part of the overall technical review program as defined in a project review plan. Pre-ship review is held at the supplier or NASA facility where the item was made and tested. | |
| language | English | |
| title | NASA-LLIS-0668 | num |
| title | Lessons Learned – Pre-Ship Review | en |
| type | standard | |
| page | 6 | |
| status | Active | |
| tree | NASA - National Aeronautics and Space Administration (NASA):;2000 | |
| contenttype | fulltext |

درباره ما