Lessons Learned - Test Stand E-1 Mishap

contributor authorNASA - National Aeronautics and Space Administration (NASA)
date accessioned2017-09-04T16:23:08Z
date available2017-09-04T16:23:08Z
date copyright02/17/2005
date issued2005
identifier otherTRWEQCAAAAAAAAAA.pdf
identifier urihttps://yse.yabesh.ir/std/handle/yse/86499
description abstractAbstract:
During welding operations at the E-Complex in support of the Full-Volume RP Construction Project at Stennis Space Center, a fire occurred as a result of welding/cutting operations being performed on Level 5 of the E-1 Test Stand. The Mishap Investigation Team concluded that the proximate cause of this Type C incident was hot welding slag igniting combustible material under and near the vicinity of the welding/cutting operation. Contractor failure to follow procedures associated with hot work permits due to schedule pressure contributed to the incident, as well as lack of training and overburdened supervisory personnel.
languageEnglish
titleNASA-LLIS-1517num
titleLessons Learned - Test Stand E-1 Mishapen
typestandard
page4
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;2005
contenttypefulltext
subject keywordsAccident Investigation
subject keywordsEmergency Preparedness
subject keywordsEnergetic Materials - Explosive/Propellant/Pyrotechnic
subject keywordsFire Protection
subject keywordsHuman Factors
subject keywordsPolicy & Planning
subject keywordsRisk Management/Assessment
subject keywordsSafety & Mission Assurance
subject keywordsTest Facility


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record