NASA-LLIS-1733
Lessons Learned – Genesis Sample Return Mishap (2004)
| contributor author | NASA - National Aeronautics and Space Administration (NASA) | |
| date accessioned | 2017-09-04T16:30:05Z | |
| date available | 2017-09-04T16:30:05Z | |
| date copyright | 02/10/2004 | |
| date issued | 2004 | |
| identifier other | BOXCQCAAAAAAAAAA.pdf | |
| identifier uri | https://yse.yabesh.ir/std/handle/yse/93390 | |
| description abstract | Abstract: The Genesis sample return mishap was attributed to a design error in which the gravity switches that activate the parachute deployment sequence were phased (oriented) incorrectly so that their mechanisms could not detect the atmospheric entry. Mission critical functions should have functional backups as well as redundant hardware. Ensure that heritage designs that have been modified are fully tested, that design engineers fully understand the system function of their hardware, and that peer reviews of critical functions achieve full fidelity. | |
| language | English | |
| title | NASA-LLIS-1733 | num |
| title | Lessons Learned – Genesis Sample Return Mishap (2004) | en |
| type | standard | |
| page | 6 | |
| status | Active | |
| tree | NASA - National Aeronautics and Space Administration (NASA):;2004 | |
| contenttype | fulltext | |
| subject keywords | Additional Categories. | |
| subject keywords | Additional Categories.Accident Investigation | |
| subject keywords | Additional Categories.Aerospace Safety Advisory Panel | |
| subject keywords | Additional Categories.Flight Equipment | |
| subject keywords | Additional Categories.Flight Operations | |
| subject keywords | Additional Categories.Ground Operations | |
| subject keywords | Additional Categories.Hardware | |
| subject keywords | Additional Categories.Mishap Reporting | |
| subject keywords | Additional Categories.Payloads | |
| subject keywords | Additional Categories.Spacecraft | |
| subject keywords | Engineering Design (Phase C/D). | |
| subject keywords | Engineering Design (Phase C/D).Spacecraft and Spacecraft Instruments | |
| subject keywords | Mission Operations and Ground Support Systems. | |
| subject keywords | Mission Operations and Ground Support Systems.Mission control Planning | |
| subject keywords | Program Management. | |
| subject keywords | Program Management.Contractor relationships | |
| subject keywords | Safety and Mission Assurance. | |
| subject keywords | Safety and Mission Assurance.Product Assurance | |
| subject keywords | Safety and Mission Assurance.Review systems and boards | |
| subject keywords | Systems Engineering and Analysis. | |
| subject keywords | Systems Engineering and Analysis.Engineering design and project processes and standards | |
| subject keywords | Systems Engineering and Analysis.Planning of requirements verification processes |