NASA-LLIS-0365
Lessons Learned - Antenna Performance Specifications Not Met
Year: 1994
Abstract: Abstract:
The system and end-to-end testing programs for the SEASAT synthetic aperture radar were impacted by schedule and cost constraints that contributed to failure to meet the primary mission objective. The development organization and the project should understand the consequences of an inadequate test program. The risks associated with any reduction of testing should be clearly documented and communicated to the project.
The system and end-to-end testing programs for the SEASAT synthetic aperture radar were impacted by schedule and cost constraints that contributed to failure to meet the primary mission objective. The development organization and the project should understand the consequences of an inadequate test program. The risks associated with any reduction of testing should be clearly documented and communicated to the project.
Subject: Cost vs. Risk Tradeoff
Show full item record
| contributor author | NASA - National Aeronautics and Space Administration (NASA) | |
| date accessioned | 2017-09-04T16:33:20Z | |
| date available | 2017-09-04T16:33:20Z | |
| date copyright | 34690 | |
| date issued | 1994 | |
| identifier other | UUAEQCAAAAAAAAAA.pdf | |
| identifier uri | https://yse.yabesh.ir/std/handle/yse/96757 | |
| description abstract | Abstract: The system and end-to-end testing programs for the SEASAT synthetic aperture radar were impacted by schedule and cost constraints that contributed to failure to meet the primary mission objective. The development organization and the project should understand the consequences of an inadequate test program. The risks associated with any reduction of testing should be clearly documented and communicated to the project. | |
| language | English | |
| title | NASA-LLIS-0365 | num |
| title | Lessons Learned - Antenna Performance Specifications Not Met | en |
| type | standard | |
| page | 2 | |
| status | Active | |
| tree | NASA - National Aeronautics and Space Administration (NASA):;1994 | |
| contenttype | fulltext | |
| subject keywords | Cost vs. Risk Tradeoff | |
| subject keywords | Prototype System Development | |
| subject keywords | Risk Management/Assessment | |
| subject keywords | Test & Verification |