Lessons Learned - KSC Checkout and Launch Control System (CLCS) - Project, Systems, SM&A
Year: 2009
Abstract: Abstract:
The CLCS project was initiated in FY 1997 to modernize the Launch Processing System (LPS) that was engineered and developed in the 1970s. The modernization was needed to ensure continued safe and dependable launch support for the Shuttle program. Per initial planning, CLCS was projected to reduce the costs for Shuttle operations at KSC, in addition to being an architecture in place that would support future planning and new program activities to occur at KSC. The CLCS project experienced many significant challenges even from the project startup (i.e., time and resources that included both funding and manpower).
This lesson document covers project/program management, systems engineering, and safey and mission assurance.
The CLCS project was initiated in FY 1997 to modernize the Launch Processing System (LPS) that was engineered and developed in the 1970s. The modernization was needed to ensure continued safe and dependable launch support for the Shuttle program. Per initial planning, CLCS was projected to reduce the costs for Shuttle operations at KSC, in addition to being an architecture in place that would support future planning and new program activities to occur at KSC. The CLCS project experienced many significant challenges even from the project startup (i.e., time and resources that included both funding and manpower).
This lesson document covers project/program management, systems engineering, and safey and mission assurance.
Subject: Additional Categories.Launch Process
Show full item record
| contributor author | NASA - National Aeronautics and Space Administration (NASA) | |
| date accessioned | 2017-09-04T17:11:58Z | |
| date available | 2017-09-04T17:11:58Z | |
| date copyright | 01/27/2009 | |
| date issued | 2009 | |
| identifier other | YTXCQCAAAAAAAAAA.pdf | |
| identifier uri | http://yse.yabesh.ir/std/handle/yse/135475 | |
| description abstract | Abstract: The CLCS project was initiated in FY 1997 to modernize the Launch Processing System (LPS) that was engineered and developed in the 1970s. The modernization was needed to ensure continued safe and dependable launch support for the Shuttle program. Per initial planning, CLCS was projected to reduce the costs for Shuttle operations at KSC, in addition to being an architecture in place that would support future planning and new program activities to occur at KSC. The CLCS project experienced many significant challenges even from the project startup (i.e., time and resources that included both funding and manpower). This lesson document covers project/program management, systems engineering, and safey and mission assurance. | |
| language | English | |
| title | NASA-LLIS-1851 | num |
| title | Lessons Learned - KSC Checkout and Launch Control System (CLCS) - Project, Systems, SM&A | en |
| type | standard | |
| page | 3 | |
| status | Active | |
| tree | NASA - National Aeronautics and Space Administration (NASA):;2009 | |
| contenttype | fulltext | |
| subject keywords | Additional Categories.Launch Process | |
| subject keywords | Additional Categories.Launch Vehicle |