Lessons Learned – Standard Change Order Cost Proposals Format

contributor authorNASA - National Aeronautics and Space Administration (NASA)
date accessioned2017-09-04T17:17:29Z
date available2017-09-04T17:17:29Z
date copyright03/02/2011
date issued2011
identifier otherZIHOEEAAAAAAAAAA.pdf
identifier urihttp://yse.yabesh.ir/std/handle/yse/140828
description abstractAbstract:
In the course of the NASA on-site management of the construction of the Ares I Mobile Launcher (ML) at Kennedy Space Center (KSC), the change orders were numerous and tended to be technically complicated, due to the magnitude of the ML project (~$140M). The NASA team dictated the use of a specific Excel format and requisite supporting data. This expedited review and facilitated negotiation. Cost proposal format should be dictated as part of the contract.
languageEnglish
titleNASA-LLIS-4620num
titleLessons Learned – Standard Change Order Cost Proposals Formaten
typestandard
page2
statusActive
treeNASA - National Aeronautics and Space Administration (NASA):;2011
contenttypefulltext
subject keywordsProgram Management .Acquisition / procurement strategy and planning
subject keywordsProgram Management.Business processes
subject keywordsProgram Management.Configuration and data management