NASA-LLIS-2916
Lessons Learned – Avionics Line Replaceable Unit Built in Tests
Year: 2010
Abstract: Abstract:
The Space Shuttle Program Orbiter Avionics Line Replaceable Unit's (LRU) were designed with limited or no diagnostic capability. The lack of fault isolation capability resulted in flight processing schedule impacts and collateral damage to flight hardware. New LRU designs need to provide an Integrated Built In Test that will verify the LRU internal components and external outputs of the LRU are functioning nominally.
The Space Shuttle Program Orbiter Avionics Line Replaceable Unit's (LRU) were designed with limited or no diagnostic capability. The lack of fault isolation capability resulted in flight processing schedule impacts and collateral damage to flight hardware. New LRU designs need to provide an Integrated Built In Test that will verify the LRU internal components and external outputs of the LRU are functioning nominally.
Subject: Acquisition / procurement strategy and planning
Show full item record
| contributor author | NASA - National Aeronautics and Space Administration (NASA) | |
| date accessioned | 2017-09-04T17:38:42Z | |
| date available | 2017-09-04T17:38:42Z | |
| date copyright | 05/10/2010 | |
| date issued | 2010 | |
| identifier other | DQQIUCAAAAAAAAAA.pdf | |
| identifier uri | http://yse.yabesh.ir/std/handle/yse/161656 | |
| description abstract | Abstract: The Space Shuttle Program Orbiter Avionics Line Replaceable Unit's (LRU) were designed with limited or no diagnostic capability. The lack of fault isolation capability resulted in flight processing schedule impacts and collateral damage to flight hardware. New LRU designs need to provide an Integrated Built In Test that will verify the LRU internal components and external outputs of the LRU are functioning nominally. | |
| language | English | |
| title | NASA-LLIS-2916 | num |
| title | Lessons Learned – Avionics Line Replaceable Unit Built in Tests | en |
| type | standard | |
| page | 3 | |
| status | Active | |
| tree | NASA - National Aeronautics and Space Administration (NASA):;2010 | |
| contenttype | fulltext | |
| subject keywords | Acquisition / procurement strategy and planning | |
| subject keywords | Engineering design and project processes and standards | |
| subject keywords | Ground processing and manifesting | |
| subject keywords | Ground support systems | |
| subject keywords | Human factors planning | |
| subject keywords | Launch support systems |